Process of Quality Check on Induction Motor
As we know that quality of product is important.
Performance or product appearance depend upon the quality of material &
components used for manufacturing of product. In Induction Motor there is two
stage of quality check. Following are the two stages of quality confirmation:
1.
Mechanical
Quality Check
2.
Electrical
Quality Check
Mechanical
Quality Check: In construction of Induction Motor in our
previous blog we see the different part of Squirrel Cage Induction motor. In
this section we discuss about how quality of different part is check &
confirm the part for further processing.
1. Motor
Frame: Motor frame is physically check. Frame dimension
inside & outside bore diameter is check. Confirm there is no any blow holes
or any damage on motor Frame. Measurement of foot mounting holes.(Std. Ref.
IS1231)
2.
End
Shield: Two End Shields are used in induction Motor i.e. DE
side & NDE side. Measurement of end shield inside & outside bore diameter.
Measurement of bearing housing diameter .Check any physical damage. If motor is
flange mounted then measure the dimensions of bore & PCD of mounting holes
& its size. ( Std. Ref. IS 2223 )
3.
Terminal
Box & Terminal Box Cover: Measure Terminal Box
& Cover dimension & check any physically damage.
4.
Shaft:
Measurement of shaft diameter & run out of shaft as per requirement .Check
dimension of key slot. Also check threading in side shaft is not damage.
5.
Rotor:
Check Rotor dimension & its run out as per requirement. Check any damage of
rotor fins. Check Skew angle of rotor is
proper or not.
6. Stator
Core: Check
dimension of stator core & Skew angle is proper or not. Also check the No.
of stator slot, its area & construction as per requirement.
7.
Bearing:
Checking of proper bearing used & bearing fix exact to required position.
There is no any mismatch or damage of bearing during fix. If Ball or Roller
bearing are used then check the proper quantity of grease used.
8. Oil
Seal or V-Seal: Physically check the proper Oil Seal or
V-seal are used & it is properly fix in required position. There is no any
damage during fixing of Oil-Seal or V-Seal.
9. Cooling
Fan:
Physically check the Fan for dimension or there is no any loose components on
fan that is used for balancing like washer or any other welded part. Also check
the no. of Fan Blade & key way dimension if available.
10. Fan
Cover or Fan Cowl: Physically check there is no any mechanical damage
.Measurement of fan cover dimensions. Finger testing on fan cover for
confirmation of IP test. ( Ref. Std. IS 4096 or IS/IEC 60034-5 )
11. Colour Shade
: Check colour shade of motor is proper. Check colour thickness by using
DFT Meter. ( Ref.Std. IS 5 or as per customer requirement )
Electrical
Quality Check: Performance of induction motor is also
depend upon the electrical parameter. Following quality testing is perform for
confirmation of electrical quality of material or component used in motor.
2. Rotor:
Check the rotor packet is proper or not .Take growler Test on rotor. This test
is useful to determine the any damage in rotor bar or any deformation in rotor
is present or not.
3. Winding & Winding Wire:
Wire used for winding is mostly copper wire. Check the insulation of copper
wire. Cut 1 Meter or some wire in spool of wire & test the resistance, High
Voltage test on that wire. Measure Break down Strength of wire is as per
requirement or not by using BDV Tester. Also perform Pinhole test on wire by
using Pinhole tester to identify the pinholes presents in copper wire. After
making the coil from wire check the dimension of copper coil . Test the
resistance of coil. Also take surge test on coil after inserting in stator
stamping. Take High Voltage Test on stator stamping.
4. Insulation Paper:
Check the insulation paper thickness is proper or not & check the there is
no any damage or insulation paper break. Take H.V. Test on insulation paper. Measure the
insulation resistance of paper. Measure the cutting size of insulation paper is
proper or not.
5. Lead Wire :
Check lead wire are properly brazed with winding & also check the proper size of lead wire used
.Terminal marking on lead wire is proper. There is no any insulation damage of
lead wire.Termial marking is proper sequence i.e. U, V, W & motor
connection star or delta is check. Lead wire connecting lug is tight or not.
6. Space Heater & Thermistor:
If Space heater or thermistor is available in the motor. Then Check the
resistance of both space heater and thermistor. Take H.V. Test on space heater.
7. Earthling Plate or Earthling Marking:
Check earthing Plate or earthing marking is on motor.
8. Name
Plate: Check motor name plate details as per require specification & it is
place on motor as per required position.
9. Final
Quality Check : After performing above all quality check .Take Routine test of the motor before packing.